ACC/421 Week 3 Textbook Solutions
$20.00
Problem P4-4
|
|
Problem P18-2
Shanahan Construction Company has entered into a contract beginning January 1, 2014, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $900,000. The following data pertain to the construction period.
2014 2015 2016
Costs to date $270,000 $450,000 $610,000
Estimated costs to complete 330,000 150,000 -0- Progress billings to date 270,000 550,000 900,000
Cash collected to date 240,000 500,000 900,000
Instructions
(a) Using the percentage-of-completion method, compute the estimated gross profit that would be recognized during each year of the construction period.
(b) Using the completed-contract method, compute the estimated gross profit that would be recognized during each year of the construction period.